North Vancouver crawl space

Hillside runoff into a crawl space during an atmospheric river. Extraction that night. Rim joist readings closed on day 5.

LossStorm, crawl-space intrusion
Property1968 split-level
Category2
AffectedCrawl space and lower rooms, 480 sq ft
Call received22:18
On site23:09
Equipment4 air movers, 2 dehumidifiers
Dry byDay 5

The living room was dry to the hand. The crawl space was not. That is the job on the North Shore after a soaker storm.

We did not sell a retaining wall on the emergency ticket. Mitigation first. Rebuild of drainage if they want it is a separate quote.

Moisture readout

Day 0

25.7%

Crawl extracted, rim joist marked

Day 5

11.9%

Target met at every point

Dry by day 5

Readings to target

Surfaces read dry days before cavities do. Stopping here is where callbacks, odour, and mould come from.

Day 0

24.1%

Extraction complete, equipment set, first readings logged

Day 1

21.8%

Readings at marked points, plan adjusted

Day 2

18.4%

Surfaces read dry. Cavities do not.

Day 3

15.2%

Cavity readings approaching target

Day 4

12.9%

One point still above target — equipment stays

Day 5

11.6% · target

Target met at every point. Equipment out, log closed.