Day 0
24.1%
Extraction complete, first readings logged

residential
A potable line failed in an upstairs bath. Water followed the joists into the living room below. Extraction the same night. Log closed on day 4 when every marked point met target.
| Loss | Supply line, second floor |
|---|---|
| Property | 1974 townhouse |
| Category | 1 (clean water) |
| Affected | 3 rooms, 620 sq ft |
| Call received | 23:41 |
| On site | 00:28 |
| Equipment | 6 air movers, 2 dehumidifiers |
| Dry by | Day 4 |
The loss was a supply line, not groundwater. Category 1 on arrival. We shut the valve, extracted standing water, and opened a small inspection hole in the ceiling below — the cavity was wet two rooms from the bath.
Equipment: six air movers and two dehumidifiers. Readings logged daily at marked points. Surfaces looked dry on day 2. Cavities were not. Equipment stayed.
Rebuild of the opened ceiling and paint was a written scope after the log closed. Neighbourhood only. Photographs are published with permission.
Day 0
Extraction complete, first readings logged
Day 1
Plan adjusted at marked points
Day 2
Surfaces read dry. Cavities do not.
Day 3
Cavity readings approaching target
Day 4
Target met. Equipment out, log closed.
Dry by day 5
Surfaces read dry days before cavities do. Stopping here is where callbacks, odour, and mould come from.
Day 0
Extraction complete, equipment set, first readings logged
Day 1
Readings at marked points, plan adjusted
Day 2
Surfaces read dry. Cavities do not.
Day 3
Cavity readings approaching target
Day 4
One point still above target — equipment stays
Day 5
Target met at every point. Equipment out, log closed.
We answer 24/7 — a person, not a service. If you would rather not talk, tell us what happened in four taps and we will call you.